fix: behind_schedule now uses time-based deviation, not just lowest progress
OLD: Showed 3 goals with lowest progress %
NEW: Calculates expected progress based on elapsed time vs. total time
     Shows goals with largest negative deviation (behind schedule)

Example Weight Goal:
- Total time: 98 days (22.02 - 31.05)
- Elapsed: 34 days (35%)
- Actual progress: 41%
- Deviation: +7% (AHEAD, not behind)

Also updated on_track to show goals with positive deviation (ahead of schedule).

Note: Linear progress is a simplification. Real-world progress curves vary
by goal type (weight loss, muscle gain, VO2max, etc). Future: AI-based
projection models for more realistic expectations.